Risk Register

Track and manage project risks across all programmes

Total Open

5

Critical

1

High Priority

2

Resolved

0

Open Risks (5)

SFS Material Delivery Delay

CriticalMitigating

Critical supply chain issue affecting steel framing delivery from main supplier. Expected 10-day delay.

Mitigation: Engaged backup supplier Metsec. Partial delivery arranged for floors 1-5. Revised programme issued.

Manchester Commercial Tower
Marcus Webb
05/04/2026
Score: 25

Skilled Labour Shortage

HighOpen

Difficulty sourcing experienced SFS installers due to competing projects in region.

Mitigation: Working with subcontractor to bring in crew from Birmingham office. Overtime approved.

Manchester Commercial Tower
Danny Fletcher
02/04/2026
Score: 16

NHS Material Specification Change

HighMitigating

Client requested change to IPS panel specification affecting lead times.

Mitigation: Change control submitted. Awaiting revised lead times from supplier.

Leeds General Hospital - Ward Block
Danny Fletcher
01/04/2026
Score: 20

Working Hours Restrictions

MediumOpen

Hospital operations limiting working hours in occupied areas.

Leeds General Hospital - Ward Block
Danny Fletcher
15/03/2026
Score: 9

Weather Risk - External Render

LowOpen

Summer heatwave forecast may affect render curing times.

Mitigation: Early morning start times planned. Shade netting available.

Birmingham Academy Extension
Marcus Webb
05/04/2026
Score: 4