Risk Register
Track and manage project risks across all programmes
Total Open
5
Critical
1
High Priority
2
Resolved
0
Open Risks (5)
SFS Material Delivery Delay
CriticalMitigatingCritical supply chain issue affecting steel framing delivery from main supplier. Expected 10-day delay.
Mitigation: Engaged backup supplier Metsec. Partial delivery arranged for floors 1-5. Revised programme issued.
Skilled Labour Shortage
HighOpenDifficulty sourcing experienced SFS installers due to competing projects in region.
Mitigation: Working with subcontractor to bring in crew from Birmingham office. Overtime approved.
NHS Material Specification Change
HighMitigatingClient requested change to IPS panel specification affecting lead times.
Mitigation: Change control submitted. Awaiting revised lead times from supplier.
Working Hours Restrictions
MediumOpenHospital operations limiting working hours in occupied areas.
Weather Risk - External Render
LowOpenSummer heatwave forecast may affect render curing times.
Mitigation: Early morning start times planned. Shade netting available.