JR Whinfrey Programme Manager
Executive Dashboard
Real-time overview across 4 active drylining and rendering programmes
Active Projects
4
Portfolio Value
£10.3M
At Risk / Delayed
2
Open Risks
5
Delayed Tasks
0
Manchester Commercial Tower
At RiskBruntwood Works
£2.9M
Due: 30 Oct 2026
Leeds General Hospital - Ward Block
DelayedNHS Property Services
£4.2M
Due: 15 Dec 2026
Birmingham Academy Extension
On TrackArk Schools Trust
£980K
Due: 07 Aug 2026
Sheffield Industrial Park - Unit 7
On TrackHarworth Group
£650K
Due: 28 Aug 2026
No milestones due this month
SFS Material Delivery Delay
criticalManchester Commercial Tower
Skilled Labour Shortage
highManchester Commercial Tower
NHS Material Specification Change
highLeeds General Hospital - Ward Block
Marcus Webb Delayed SFS Installation - Floors 1-5 due to material delivery issue
Manchester Commercial Tower • 5 Apr at 09:30
Lisa Chen Auto-rescheduled 18 downstream tasks due to SFS delay
Manchester Commercial Tower • 5 Apr at 09:31
Marcus Webb Added critical risk: SFS Material Delivery Delay
Manchester Commercial Tower • 5 Apr at 08:15